Thanks to generous voter support, we’ve been working to tackle some long-term facility maintenance needs this summer. Contractors have begun working on the Washougal High School roof, and will be busy through early September replacing the 150,000 square feet of roofing with a composition shingle roof. We’re excited to get this important work started, so students stay safe, warm and dry this coming winter!
Projects to replace corridor flooring at Gause and Hathaway will start in late June, and the heating systems and HVAC controls at WHS will be starting in the early summer.
Security system updates for schools will include additional measures to keep students safe. The district is installing newer security systems at WHS, Gause, Cape, and CCMS that match those installed already at the rest of our schools. The updated systems will include new lockdown buttons and notification systems. These systems will provide both internal and external indicators that align with the Standard Response Protocol system used by schools around the county.
Project 1 – WHS DDC Controls upgrade
Environmental Controls (ECC) is working to install the new DDC Controls for the Heating, Ventilation, and Air Conditioning system at Washougal High School. The HVAC Controls at Cape and CCMS were upgraded this spring, with work on track to be finished by June 30. Funding for the Cape/CCMS project was provided by a Washington State Department of Commerce Grant. These projects will modernize the facility management software that keeps students and teachers warm in the winter and cool in the summer.
Budget Update: Original project budget: $550,000. Updated budget: $625,000
Project 2 – WHS Boiler Replacements
- Designer: Windsor Engineers
- Contractor: Stewart Mechanical
- Timeline: Project starts in July, will wrap up in September
Update #1 6-3-2025: Design is complete, Demolition will begin once school lets out.
Update #2 6-23-2025: Demolition of the three existing gas-fired boilers is underway. The new boilers will arrive soon for installation.
Budget Update: Original project budget: $760,000. Updated budget: $521,000
Project 3 & 4 – Security Systems and ADA Doors
- Designer: NIS
- Contractor: GB Manchester
-
- Security system updates for schools will include additional measures to keep students safe. The district is installing newer security systems at WHS, Gause, Cape, and CCMS that match those installed already at Hathaway, Columbia River Gorge Elementary, and Jemtegaard Middle School.
- The updated systems will include new lockdown buttons and notification. These systems will provide both internal and external indicators that align with the Standard Response Protocol system used by schools around the county.
- Update #1: Design is complete, They’ve started swing shift work doing rough-in, device installation will start in July. 5 locations in progress.
- Update # 2: Crews have pulled in wiring for the new security system
Budget Update: Original project budget: $735,000. Updated budget: $1,010,000
Project 5 – WHS Roof Replacement
- Designer: Professional Roofing Consultants PRC
- Contractor: Carlson Roofing
- Timeline: Project starts in May, will wrap up in September
Update #1 6-3-2025: Design is complete, Started at the end of May, work is focused over gym and cafeteria areas to not disturb classrooms as the school year finishes. Work is ongoing, at this moment in time they’re half way through approximately 10% of the area. The project plan is phased with portions of the roof completing as other portions are removed and rebuilt until project completion.
Update #2 6-23-2025: Demolition of existing roof above two story classroom wing is about half done. New shingles have been placed on the small gym and weight room roofs.
Budget Update: Original project budget: $3,600,000. Updated budget: $2,708,000
The district worked with construction and building experts to run a competitive bid to replace the Washougal High School roof. The district asked for bids for roofs that would be a mixture of composition shingles and metal, and options for an all shingle roof. The bids received reflected significant increases in costs, which made the metal roofing unaffordable.
The board has approved a contract to proceed with an all composition shingle roof.
Project 6 – Gause & Hathaway Carpet replacement
-
- Update #1:
- Contractor: Beresford Company
- Timeline: Project starts in June wraps up in August
- Update #1:
Update #1 6-3-2025: On track for completion in August, carpet has been ordered and delivered. Crews are preparing to demolish old carpet once school is out.
Update #2 6-23-2025: Demolition of existing carpet at Gause is about 75% complete.
Budget Update: Original project budget: $280,000. Updated budget: $182,000